AGENDA
EUGENE WATER & ELECTRIC BOARD
SPECIAL BOARD MEETING
(WORK SESSION)
EWEB BOARD ROOM
DECEMBER 5, 2000
6:00 P.M.
- 2001 Legislative Session - Libby Henry,
Legislative Representative
REGULAR BOARD MEETING
7:30 P.M.
- Agenda check (President
Bishop)
- Approval of Consent Calendar (Items will
be approved by one motion and without discussion. If discussion is
required, specific items will be removed from the Consent Calendar
and considered separately.)
- Correspondence (5 min.)
- Items from Board Members (5
min.)
- Public input
- 2001 Budget and Work Plan - Dick Varner,
Fiscal Services Supervisor (Presentation - 10 min./Discussion -
10 min./Information)
- Public Hearing on 2001 Budget and Work Plan
- 2001 Budget and Work Plan - Dick Varner
(Action)
- Groundwater study results and recommendations
- Brenda Sirois, Water Resources Planner,
(Presentation - 10 min./Discussion - 5
min./Information)
- Public Hearing on Groundwater Development
- Groundwater Development Resolution -
Brenda Sirois (Discussion - 5
min./Action)
- 2001 Legislative Principles - Libby Henry
(Presentation - 5 min./Discussion - 5 mi./Action)
- Public Agency Network Telecommunications Pricing Policies -
Debra Wright, Risk/Purchasing Manager
(Presentation - 10 min./Discussion - 5
min./Action)
- Winter Reliability issues - Dean Ahlsten,
Electric Engineering Manager and Dick Varner, Fiscal Services
Supervisor (Presentation - 20 min./Discussion -
10 min./Action)
- Execution of the Forward Power Sale as a financial
transaction - Dick Varner (Presentation - 5
min./Discussion - 5 min./Action)
- Items removed from Consent Calendar
Consent Calendar
December 5, 2000
RESOLUTION
- Revolving Line of Credit for the Energy Conservation
Loan Program (see memo from Cathy Bloom for
details).
CONTRACT INCREASES
- National Wood Treating - Pole Testing/Treating -
Electric Operations - Electric Division. This
is the third year of a three-year contract with National Wood
Treating for testing and treating EWEB's electric pole plant. The
budget for this year's work was under estimated by $16,000. We
would also like to extend the contract with National Wood Treating
for an additional two years as provided by ORS statutes. Estimated
cost - $40,000 per year. Total contract amount through December
31, 2002 is $96,000. Contact person is Brad Edwards, 484-2411,
ext. 3656.
- SCT Utility Systems, Inc. - Banner CIS Transition -
Information Services - Corporate Services. This Business
Services Agreement resolves a payment dispute with SCT and secures
400 hours of Professional Services for EWEB as its portion of the
settlement. These hours are to be used before October 31, 2002 and
are unrestricted in the types of services to be used. EWEB
anticipates using these hours for projects currently in the 2001
budget. EWEB will pay outstanding invoices in full, an amount of
$135,720. The 400 hours of Professional Services have a value of
$78,000. Contact is Terry Bequette, IS Manager, at 484-2411, ext.
3364.
- Duke Engineering & Services, Inc. - Stone Creek
Hydro Environmental Compliance - Environmental Management -
Corporate Services. Duke Engineering has served as EWEB's
project consultant since EWEB purchased the Stone Creek
Hydroelectric project in 1992. Under present contract, in effect
since August 1998, Duke provides EWEB with environmental
consulting services in support of on-going requirements of our
Stone Creek Hydroelectric Project's FERC License and State Water
Right Permit. Major work items include: stream gauge monitoring
and maintenance to assure compliance with instream flow
requirements, expanded Corydalis (sensitive plant) monitoring
based on an approved, revised sampling plan, technical support to
EWEB in project coordination and negotiations with U.S. Forest
service and ODFW, and monitoring and compliance reporting.
Existing contract has been amended annually to add budgeted monies
($40,000 in both 1999 and 2000). The present contract, running
through mid-August 2001, is planned to be amended for
renewal.
Due to the re-occurring nature of much of the required work, the
action requested is for approval of $130,000 to cover the total
amount of the contract for the remaining three years of a five-year
period, from January 2001 through December, 2003. For 2001, $40,000
has been budgeted. Estimated costs for 2002 and 2003 are $50,000 and
$40,000, respectively. Monies are higher for 2002 due to additional
Corydalis monitoring required. Contact person is Tim Downey,
Environmental Dept. 484-2411, ext. 3304.