Related News
Related News
-
EWEB opens application for 2024 Electric Mobility Community Grants
Grant awards of up to $30,000 to cover costs associated with electric mobility projects.
Find Out More -
The Big Freeze 2024: After Action Report
Winter 2024 was one for the records books, and we'll look back on it for years to come and say, "That was a doozy!" The back-to-back January Ice Storms caused widespread damage to EWEB’s service territory, affecting approximately 38,000 customers. Preliminary repair costs were over $8 million, and additional repairs to transmission lines are still required.
Find Out More -
Fixing the Unseen: Water Pipeline Replacement in Unincorporated Eugene
Learn more about EWEB's methods for monitoring and replacing aged water pipelines.
Find Out More -
Spring Cleaning? How about Spring Emergency Preparedness!
Spring is officially here and that means the plants are blooming, the sun is (sometimes) shining, and the grass is green! We've had our fair share of severe weather already, but spring weather is notoriously unpredictable. While you're in the midst of spring cleaning and garden care, consider completing these emergency preparedness tasks.
Find Out More -
EWEB General Manager Delivers 2024 State of the Utility
General Manager Frank Lawson delivered his address at the March 5 public Board of Commissioners meeting
Find Out More -
Nine days without power: My ice storm story as an EWEB customer and employee
While beautiful and peaceful, buying a home on the edge of the forest and surrounded by trees has its tradeoffs. Moving “upriver,” I knew there would be more threats to prepare for, including Mother Nature’s seasonal surprises.
Find Out More -
Reenergized McKenzie River Valley transmission lines allow EWEB crews to restore power upriver
On Friday, a majority of EWEB crews tackled power restoration efforts upriver, after federally managed transmission lines were reenergized Thursday.
Find Out More -
EWEB estimates one week to complete power system restoration
On Wednesday, EWEB crews restored power for about 10,000 customers by repairing large equipment first.
Find Out More -
Second round of ice and ensuing thaw prompt mass power outages
On Wednesday, all EWEB crews, who have been working nonstop since Saturday, traversed EWEB’s service territory assessing the damage and restoring transmission lines and main power feeders.
Find Out More -
Power restored at EWEB’s water treatment plant
Crews restored electric power at EWEB's Hayden Bridge Water Filtration Plant Monday evening, allowing operators to switch off the generators and rely again on the grid. Meanwhile, EWEB crews brace for additional outages amidst second round of ice and during the coming thaw.
Find Out More -
EWEB crews making downed lines safe and restoring power across Eugene and the foothills
As EWEB works to restore electric service to customers affected by the ice storm, the customer-owned utility is following established policies and its “hierarchy of repair” to prioritize repairs that restore electric service to the greatest number of customers.
Find Out More -
Leaburg Decommissioning Action Plan
Plan details next steps through regulatory processes to begin dismantling Leaburg Dam by 2032.
Find Out More -
What’s ahead in 2024: General manager’s message to EWEB customer-owners
At the start of the new year, we back at accomplishments from 2023 and look ahead at what's to come in 2024.
Find Out More -
Currin Substation: End of year update
EWEB Engineer Philip Peterson explains what's been happening in the final stretch to complete the substation rebuild.
Find Out More -
EWEB 2023 year in review
In 2023, EWEB invested in our community with grants, rebates and an array of other programs and measures aimed at fulfilling our core values of safety, reliability, affordability, environmental responsibility and community/culture.
Find Out More - Show More
EWEB achieves power restoration milestone over the weekend
January 22, 2024 • Aaron Orlowski, EWEB Communications
EWEB crews worked through the weekend to continue restoring power for customers and by Monday morning only 8% of customers who had lost power at the peak of the ice storm still needed their power restored.
Outages peaked on Wednesday morning at 24,000 customers, after a second barrage of ice struck the region. As of Monday morning, about 1,900 customers remained without power, meaning that EWEB had restored power to 92% of those who originally lost it.
“Getting over 90% is a major milestone for our crews, who have been working 16-hour days for more than a week straight. But much of the hardest work remains to be done,” said Tyler Nice, EWEB electric operations manager. “This progress and the support from the community gives us fuel to keep working as quickly and safely as possible to restore power for our remaining customers.”
EWEB finished repairs and re-energized its transmission line up Camp Creek Road late Sunday evening and expects that progress to result in larger restorations in the area Monday. At the same time, for a significant number of these last customers in the area, there will be work ahead to get their power on due to challenges accessing electrical equipment and the damage suffered.
Seventeen crews, including 11 contract crews, are in the field working to get the power back on. All told, about 250 EWEB staff are solely dedicated to working on the emergency.
Even though the ice has melted and EWEB has restored power for tens of thousands of customers, weakened tree limbs are still falling and causing additional outages. For instance, on Saturday, a tree limb came down and knocked out power for more than 2,000 customers in the Willakenzie area. Crews responded to the outage, made it safe, assessed the problem and restored power.
On Sunday, the majority of crews worked upriver in the McKenzier River Valley, replacing poles and preparing for restoration in the Camp Creek area ahead of that area’s main transmission line being energized. Crews re-energized the transmission line from Thurston to Walterville late Sunday night, one of the first steps to complete before power can be restored for most of the remaining upriver customers.
The ice storm incurred enormous damage on the lower McKenzie River Valley, where crews are working to repair large transmission and feeder lines. Some back roads remain inaccessible, hindering progress. On Monday, crews made progress in the Deerhorn, Camp Creek, and Cedar Flat areas.
After Wednesday’s peak, crews initially made rapid progress repairing large equipment that serves thousands of customers. Now that crews have started repairing small pieces of equipment that serve clusters of homes, the pace of restorations has slowed by numbers, but not the effort or dedicated resources. Especially in town, the remaining work is on tap lines that serve individual neighborhoods, generally less than 20 customers. These are often the most time-consuming repairs.
As these smaller areas are restored, single customers may experience outages even after their neighbors are energized due to damage at their property. It’s important for customers to look at their weatherhead, service entrance and meter base to see if it is damaged. In some cases an electrician may need to be contacted by the customer to make needed repairs, and coordination with EWEB to make safe and re-energize once the repairs are made.
EWEB projects that crews will complete the bulk of restoration of the power system by Thursday. The vast majority of affected customers have already seen their power restored, but much work remains for the rest of the week. A small number of customers in areas with difficult repairs and severe damage, such as more remote areas upriver, should prepare to be without power past Thursday.
Customers can check EWEB’s outage map for more details: eweb.org/outagemap